Preparing a Site for Cold Room Installation

Site preparation for a cold room is the civil, structural and service work that has to be finished before insulated panels, doors and refrigeration equipment can be installed and commissioned. It covers the slab, the space around the room, the power and drainage connections, and the access route for panels that often run 6 to 11 m long. A slab that needs another three weeks to cure pushes panels, piping and commissioning back by the same three weeks, so the site survey sets the schedule.

This article lists what a site has to provide, which items go wrong most often, and what to check before the first panel truck arrives. It is written for food factories, distributors and contractors who are about to build a room and want the civil works to match the equipment they are buying.

What the site survey has to record

A useful survey is a set of measurements, not a set of impressions. We ask for the following before drawings leave the office:

  • Internal length, width and clear height of the room, plus the height to the underside of the roof or ceiling structure.
  • Slab level relative to the finished floor outside, and flatness measured with a straightedge over 2 m and 3 m.
  • Concrete strength and age. A slab poured last week cannot carry a loaded room today.
  • For freezer rooms: underfloor insulation type and thickness, vapour barrier, and whether heating cable or a glycol loop is already installed.
  • Drain positions, pipe route and the fall available to the outside.
  • Door positions, threshold heights, corridor widths and the turning space for pallet trucks.
  • Power supply: voltage, phases, frequency, breaker size, meter position and the cable route to the plant room.
  • Condenser location, clearance in front of the coil, and the pipe distance back to the evaporators.
  • Delivery route: gate width, doorway widths, lift size, overhead cables, and whether a crane or telehandler can reach the room.

Two items change from country to country: supply voltage and frequency, and the local rules for electrical and refrigeration work. Much of Asia and the Gulf runs 380 to 415 V at 50 Hz; parts of Southeast Asia and the Philippines run 220 V or 380 V at 60 Hz. Motors, controls and protection have to be ordered for the site, not assumed. Rules also change, so confirm the current requirements with your importer or local authority before the equipment ships.

The floor slab and the freezer floor

The floor causes more rework than panels, doors and piping combined. Insulated panels are made to tight tolerances and assembled dry; they cannot correct a slab that slopes, steps or has not cured. The room sits on the slab, the doors sit on the threshold, and the drainage sits at the low point, so every error in the floor is repeated at the door.

Level, flatness and strength

For a general room, a slab within about ±5 mm over 2 m is workable. At door thresholds, especially sliding doors and high-speed doors, tighter is better: around ±3 mm over 3 m, so the seal meets the floor along its whole length. A 10 mm step at a threshold lets warm air and water through, wears the gasket and turns into ice in a freezer. Concrete should be fully cured and strong enough for the loads; a floor carrying racking and pallet trucks is usually specified at C25 or C30, and the structural engineer's number governs.

Freezer floors need more than concrete

A ground-supported freezer needs insulation under the slab, a continuous vapour barrier, and a way to keep the ground below freezing from lifting the floor. Frost heave is slow and expensive: the slab rises, the panels lift, the doors stop closing. The usual answers are an electric heating cable or a glycol loop under the slab and around the door opening, or a ventilated void. Which one fits depends on soil, water table and the price of electricity, and should be decided at design stage, not after the concrete is poured. Floor drains inside a freezer also need a heated drain line or a trapped drain in a heated box, or the drain itself becomes an ice plug.

ItemWho normally does itWhat to checkIf it is wrong
Slab level and flatnessCivil contractor±5 mm over 2 m general, ±3 mm over 3 m at door thresholdsDoor seals leak, panels need packing, floor drains do not fall
Slab strength and cureCivil contractorStrength per structural design, full cure before loadingCracks under racking, panels distort, schedule slips weeks
Underfloor insulation and vapour barrierCivil or specialistContinuous barrier, correct thickness, no gaps at edgesIce build-up under the floor, frost heave, energy loss
Anti-frost heating or glycol loopCivil or MEPCoverage under room and door zone, tested before slab coverFloor lifts in service, doors jam
Drainage and fallCivil or MEPFall to drain, heated or trapped line in freezer, accessible outsideStanding water, ice plug, product damage
Power supply and earthingElectrical contractorVoltage, frequency, breaker size, cable route, earth resistanceEquipment cannot start, nuisance trips, safety risk
Access and liftingMain contractorPanel route clear, crane or telehandler position, storage area flat and dryPanels damaged or cannot be delivered

Space above, around and in front of the room

Panels need a structure to hang from. A panel ceiling is carried on hangers fixed to the building structure at the panel joints, so the structural grid, the position of beams and the space above the ceiling all matter. Leave 300 to 500 mm between the panel ceiling and the structure for lights, cables and air movement; more if there are ducts or a sprinkler line. Hangers should not be fixed to sprinkler pipe or cable tray.

Around the room, leave working space for panel joints, door frames and future service. In front of a sliding door, allow about 1.5 m clear so the leaf can park and a pallet truck can turn. At a dock, the door threshold, ramp and leveller heights have to line up with the truck bed, and the seal at the top of the opening has to close against the vehicle, not against air.

Height is the other constraint. A room designed to 4 m clear needs a building with enough headroom for the panel thickness, the ceiling hangers and the lights. If the roof is too low, the choice is a lower room, a different ceiling system, or a building change. Raising a roof after the panels are ordered is the expensive version of this conversation.

Power, drainage and the route for panels

Refrigeration equipment is ordered for a supply, not the other way round. A 380 V 50 Hz condensing unit will not run on a 60 Hz supply, and a unit sized for 220 V single phase will not start on the wrong breaker. Give the equipment supplier the site voltage, phase, frequency and available breaker, and ask for the starting current and cable size. Long cable runs add voltage drop, and undersized cable adds callbacks.

Locate the control panel outside the room, near the door, in an area that stays dry and does not sit in direct sun. Leave space for a person to stand and work in front of it. Condensers need airflow: keep the coil clear, avoid boxing the unit into a corner, and respect the clearance the unit manufacturer publishes. Pipe runs from a remote condenser to the evaporators should be short and should follow the manufacturer's limits for length, lift and oil return.

Panel delivery is a logistics problem before it is an installation problem. Standard panels come in widths of about 1 m and lengths that follow the room height or the roof span, and the longest panel may not pass a stairwell, a lift or a 900 mm doorway. Check the route with a tape, or split the panels into shorter modules at the manufacturing stage. Panels should be stored flat, dry and off the ground, not stood on edge in the sun, and not stacked beyond the manufacturer's limit.

Installation sequence and what to send for a quote

The sequence that keeps a project on schedule is short. Slab finished and checked, services roughed in, panels and doors installed, refrigeration and electrical connected, drains and thresholds finished, then commissioning with a temperature pull-down and a door test. Each step has a sign-off, because the next trade builds on the last. Installation itself is usually two to four weeks for a small to medium room once the slab and services are ready; larger rooms and blast freezers take longer. Final dates are to be confirmed against drawings.

For a quotation, send the room size and the temperature of each room, the product and daily throughput, site photos, the slab or floor drawing, the available power, door traffic and the destination port. We work with a network of vetted manufacturers and supply panels, doors, condensing units and controls as one package. Installation and commissioning can be done by trusted installation teams, including overseas. If the civil works are still being planned, send the survey list above and we will mark what the building has to provide.

More detail on the build sequence is in Cold Room Construction Process. Panel specification and thickness are covered in Cold Room Panel Thickness. Product pages for the main items are cold room engineering, insulated panels, high-speed doors and split control panels.

Frequently Asked Questions

Can a cold room be installed on an existing concrete floor?

Often yes, if the slab is level, fully cured and strong enough for the loaded room. For a freezer, the slab also needs underfloor insulation, a continuous vapour barrier and anti-frost heating or a glycol loop. If those are missing, the options are insulated floor panels on a structural base or a new slab. A site survey confirms which route fits.

How level does the floor need to be before panels arrive?

About plus or minus 5 mm over 2 m is workable for a general room. At door thresholds, especially for sliding and high-speed doors, aim for about plus or minus 3 mm over 3 m so the seal meets the floor along its full length. Measure with a straightedge and record the readings before the panel delivery date.

Do I need underfloor heating for a freezer room?

Most ground-supported freezers do, to stop frost heave lifting the slab and the panels. The usual choices are an electric heating cable or a glycol loop under the slab and around the door opening, or a ventilated void. The right choice depends on soil, water table and running cost, and should be settled at design stage.

How much clear space is needed above the panel ceiling?

Leave 300 to 500 mm between the panel ceiling and the building structure for lights, cables and air movement, and more where ducts or sprinkler lines run. Panel ceiling hangers fix to the structure at the panel joints, so the structural grid and beam positions matter as much as the total height.

Can insulated panels be moved through a normal doorway?

Often not. Panels run 6 to 11 m long and may not pass a stairwell, a lift or a 900 mm door. Check the whole route with a tape before ordering, or ask for the panels to be split into shorter modules at the manufacturing stage. Panels should be stored flat, dry and off the ground.

How long does cold room installation take?

Typically two to four weeks for a small to medium room once the slab and services are ready. Larger rooms, blast freezers and sites with long pipe runs take longer. Final dates are to be confirmed against the approved drawings and the site programme.